LOMAX Elementary School - La Porte I.S.D.
La Porte TX - June 2008
RAM JACK Foundations/Houston was contracted by STERLING STRUCTURES, an Engineering & General Contractors Group, to provide our helical steel pilings to solve the following problem
The LOMAX Problem - Drilled Concrete Piers Failed - Settled 6"
LOMAX Engineers Foundation Repair Plan & Contractors Shop Drawing
The LOMAX Solution: Install 49 helical piles & cut 27 drilled concrete piers
The LOMAX Results: This project is Work in Progress and will be completed the first week in July. Final photos will be posted upon completion.